phase 1: Pre study► Searching for land plots and negotiations with owners private as well as City; ► Draw up purchase agreement in cooperation with local lawyer; ► Make up calculations and budget charts; ► Make up all drawings and documents for tender process; ► Take care of the environmental approvals; ► Negotiations with Contractors and draw up Contract; ► Purchasing of the parts of the Construction and technology as is decided to not be a part of the Main contract; ► Control and checking of all design and permissions such as EIA, IPPC, territorial permission and building permission. | phase 2: Construction► Control of the construction works together with local supervisors both for the buildings and for the technology; ► Responsible for design meeting, site meetings and participation in meetings required by the Client; ► Following up of all costs and report to the Client; ► Consulting support. | phase 3: Handing over► Authority inspections; ► Completion inspection; ► Final approval for running of the factory, including technology; ► Keeping contact with customer even after the project is finished. |
|